Here is a closer look at a warehouse we built for Shree Property Holdings, for general use. You can head over to their website if you’re interested in letting this property.
The project took a total of 13 weeks from order to completion, which included working through the industry strike. We were requested to keep internal column spacing to a minimum so if you visit this warehouse you will find internals across the 60m span, at every alternate bay so the effective minimum clear area equalled 750m2. 3m tilt up concrete panels and columns were used around the perimeter to expedite the building work.